Alpharetta Center II

Scope of Project This project built a 2-story 3, 500 SF expansion onto the East of the existing 49,500 SF Alpharetta facility built in 2010. The second floor of the expansion is a new classroom and the lower floor is for a new data center. The project includes:
  • a new rainwater system,
  • a terrace expansion as well as a new chiller,
  • standby generator, and
  • associated electrical services to serve the data center. The data center itself is being built out under a different project.
Location 3775 Brookside Parkway, Alpharetta, GA 30022
Start Date June 2013
Project Number 088-014-12
Completion Date November 20, 2013
Project Status Completed
Project Manager Keith Martin/ Craig Wertz
Design Firm Lord, Aeck & Sargent
Engineering Firm Concord Engineering
Contractor Potts Construction
Other Firm(s) Epsten Group (Commissioning)
Alpharettal II Slideshow 

Piedmont North Dining

Scope of Project This project built a 3,300 SF addition onto the front of Piedmont North Building ‘A’. At 175 Piedmont North addition facilitated kitchen modifications to accommodate increased service of the kitchen.
Location 175 Piedmont Avenue, Atlanta,GA 30303
Start Date November 2010
Project Number 092-034-11
Project Status Completed
Project Manager Brian Carroll

Library South - CURVE

Scope of Project This project was for a build-out of approximately 3,600 square feet in the existing Library South Building for a Collaborative University Research & Visualization Environment. The space is highly visible with a retractable glass wall front that allows overflow for special occasions to expand into the existing library lobby. This space provides for in depth research by Faculty, Graduate Students and Under Graduate Students in areas that need cutting edge digital technology and advanced visualization software. This is accomplished by using the 24’ long by 4’-6” high LCD video wall with touch capacity. There is also an 84” Ultra HD (4K) touch screen, six small group workstations, and a Graduate Assistant help desk. The main two displays use fiber optic technology & the Library hopes to convert the six group workstations to fiber optic eventually.
Location Library South, Second Floor
Start Date March 28, 2013
Project Number 020-091-13
Completion Date June 16, 2014
Project Status Completed
Project Manager Suzanne Dunn
Design Firm Collins Cooper Carusi Architects Inc.
Contractor New South Construction Company
Other Firms Cinemassive Displays
Curve Project Slideshow